MT. VERNON TRAIL PROJECT

The Mt. Vernon Trail Project (pictured below) begins construction this month, April, 2022, on CR 200 West through the Mt. Vernon School Corporation campus. The safety improvement includes traffic signals & crosswalks. This phase of the project is projected to wrap up in/by November, ’22.
The Mt. Vernon Trail Project will consist of a 10 feet wide asphalt trail, with a grass buffer between the trail & existing roadway. There will be pedestrian scale lighting, as well as benches placed, along the entire corridor.
In 2023, construction along the west side of Maple St./Fortville Pike, from Garden St. to CR 200 West will take place. During this phase of construction, improvement to the Fortville Pike/CR 200 West intersection will occur.
Scheduled for 2026, will be the final leg of the trail project, connecting the Fortville Pike/CR 200 intersection to the existing trail developed by the Mt. Vernon North subdivision.